Bolt Construction, Inc. has been awarded a subcontract for an expansion of the existing jet fuel hydrant loop at the Rickenbacker International Airport in Columbus, Ohio. The project will include installation, testing and flushing of over 2,700 feet of 12” diameter piping, fuel hydrant pits, high point vents, low point drains, and surge suppressor pits.
Bolt Construction has been awarded a subcontract to complete Phase 3 jet fuel piping for the Fed Ex Cargo Expansion Project at the Indianapolis Airport Facilities. This project extends double wall piping installed by Bolt in the first 2 phases of this Apron Expansion for future cargo use.
January/February 2008
Bolt Construction, Inc. was recently awarded a contract to complete improvements to the existing fuel farm at Charlotte Douglas International Airport. The project includes new 30” suction and 10” fill piping for (2) new 30,000 barrel tanks.
Bolt Construction work scope will include installation of a 10,000 gallon underground product recovery tank, (1) pre-filter, (3) sump separators and a 5,000 gallon oil water separator. Bolt will be responsible for system startup, commissioning and training of personnel on new system per project specifications.
2008
Bolt Construction continues to work with Marathon Petroleum Company to expand ethanol capabilities throughout their system. |